Selection
of Dam Site & Various Surveys for Site Selection:
Objectives
and Scope
The
objectives and scope of the Survey was to enhance the WCD Knowledge Base by
broadening the indepth studies already sanctioned by the Commission. The Survey
aimed at complementing and supplementing the WCD work programme components in a
way that added value and consequence to the arge dams debate.
This
section of the report sets out the key Survey objectives and scope of work
undertaken. It concludes with the limitations of the Survey.
Objectives
The
primary objectives of the Survey were:
·
to seek broader
patterns and trends relating to the performance, social and environmental
impacts, and decision-making aspects of large dams than is otherwise possible
with only the 8-10 focal dam/basincase studies, thematic reviews, regional
consultations, and submissions;
·
to provide a
better indicator of regional experience than is currently available, through
the emphasis on representation of all the major regions of the world in the
sample; and
·
to allow a broad
entry point to the emerging evidence from the WCD integrated Knowledge Base.
A
secondary objective of the Survey was:
·
through use of
the Survey questionnaires, to generate an awareness among large dam owners and responsible
institutions regarding the minimum threshold and type of data that should be
monitored and recorded accurately, responsibly and reliably
Scope
A variety of large dams of different
types (eg storage, run-of-river), ages (eg dams from the 1930.s through the
1990.s), functions (eg water supply, irrigation, hydropower, flood control,
multipurpose and other), heights, areas, ownership (eg public, state and
private), and regional locations were included in the Cross-Check Survey. Each
dam questionnaire provided date records with time series dimensions where feasible.
Analysis was performed on the full set and on specified sub-sets of dams in the
sample. Large dams have been added from previous studies or surveys but new
data for these dams was collected.
The
collection of data for all large dams in the Survey sample was conducted via a
set of questionnaires including multiple categories and criteria for reporting.
Previous experience and studies stating the inadequacy of questionnaire surveys
for capture of intended information if too elaborate in design, influenced the
nature of the questions posed in the Survey questionnaires. Information was
often requested through specified lists aimed explicitly at minimising the
level of detail required for reporting, and thus minimising barriers to
provision of data and potential misinterpretation. Consequently, the scope n of
the issues assessed in the Cross-Check Survey was purposely limited.
Data Collection Procedure
Data
for the focal and non-focal dams was collected in conjunction with the
execution of the case studies, while information for dams drawn from other
databases underwent supplementation and verification. The data for the
complementary subset of large dams was collected by commissioned contributors
and/or submitted by parties with access to the required information. The
approach for developing the data records for the Cross-Check Survey has
included research of published reports and secondary data sources available in
the public domain, as well as contact with the following types of organisations
by requesting information on standardised forms:
I.
dam operators and
utilities;
II.
key government
departments responsible for the project (eg Ministry / Department of Irrigation
/ Power of State or National government; or appropriate river basin development
authority);
III.
local
institutions/universities that may have conducted research on the dam;
·
local
NGOs/networks working on dams at the state / national level;
·
NGOs/networks
with a regional and/or international focus on dams issues;
IV.
industrial/engineering
firms with international experience and involvement in dams (with
permission of the host country);
V.
multilateral and
bilateral agencies for data on large dams available with them;
VI.
International professional associations (ICOLD, ICID, IHA, IEA)
with access to data.
All
submissions contributing to the final analysis of the Survey were required to
include data accessed from at least
two independent source documents. During the
internal review process all contributors were requested to fill in a data
source matrix to ascertain the degree of material referenced for each questionnaire.
Moreover, contributors were requested to invite participation and cite any
divergent perspectives from stakeholders where possible.
Site Selection
During the
feasibility studies, the preliminary site selection will be dependent on the
project
purposes within
the Corps’ jurisdiction. Purposes applicable to dam construction include
navigation, flood damage reduction, hydroelectric power generation, fish and
wildlife enhancement, water quality, water supply, and recreation. The
feasibility study will establish the most suitable and economical location and
type of structure.
Investigations
will be performed on:
1.
Hydrology
2.
Meteorology
3.
Relocations,
4.
Foundation
5.
Site
geology
6.
Construction
materials
7.
Appurtenant
features,
8.
Environmental considerations
9.
Diversion methods.
Selection
factors.
(1)
A concrete dam requires a sound bedrock foundation. It is important
that the bedrock have adequate shear strength and bearing capacity to meet the
necessary stability requirements. When the dam crosses a major fault or shear
zone, special design features (joints, monolith lengths, concrete zones, etc.)
should be incorporated in the design to accommodate the anticipated movement.
All special features should be designed based on analytical techniques and
testing simulating the fault movement.
(2) The topography is an important factor in
the selection and location of a concrete dam and its appurtenant structures.
Construction as a site with a narrow canyon profile on sound bedrock close to
the surface is preferable, as this location would minimize the concrete material
requirements and the associated costs.
(3)
The criteria set forth for the spillway, powerhouse, and the other
project appurtenances will play an important role in site selection. The
relationship and adaptability of these features to the project alignment will need
evaluation along with associated costs.
(4) Additional factors of lesser
importance that need to be included for consideration are the relocation of existing
facilities and utilities that lie within the reservoir and in the path of the
dam. Included in these are railroads, powerlines, highways, towns, etc. Extensive
and costly relocations should be avoided.
(6)
The method or scheme of diverting flows around or
through the damsite during construction is an important consideration to the
economy of the dam. A concrete gravity dam offers major advantages and potential
cost savings by providing the option of diversion through alternate
construction blocks, and lowers risk and delay if overtopping should occur.
Outline of the survey methods:
Generally,
a subsurface dam site is selected according to the following procedure:
1)
Interpretation of satellite images and aero-photographs
2)
Geological and topographical survey by preliminary exploration
3)
Estimate of the geological structure by geophysical surveys such as electric
soundings
4)
Verification of the geological structure by test drillings and permeability
tests
5)
Estimate of the flow mechanism of groundwater by observation of groundwater
level
Geological studies:
This is carried out to
collect data regarding
1.
Geological features folds, faults, fissures etc their
nature and extent.
2.
Water tightness of the reservoir basin
3.
Existing and potential slide area
4.
Assessment of valuable minerals in reservoir area
5.
Ground water condition
6.
Seismic conditions etc.
Bore hole logging and testing should be utilized to enhance the amount
of information obtained from each hole drilled. Certain techniques work better
in some environments than in others; thus, the following techniques listed must
be utilized discriminately according to their applicability to the site conditions.
Bore hole logging systems include caliper logs, resistivity logs, SP logs,
sonic logs, radioactive logs, etc.
Foundation Studies:
Foundation Investigation
for earth, rock fill and masonry dams includes investigation to determine
properties of foundation soil, hidden weak spots and shear zones etc and depth
of overburden.
Usual methods of
exploration include
◦ Bore holes
◦ Excavation of open pits
◦ Tunneling into the side of the valley
◦ Core drilling
Meteorological studies:
On the watershed plan,
normal annual isohyets (rain fall contours) location of rain gauge stations,
gauge and discharge sites and interprovincial boundaries are supposed to be shown.
·
Assessment of rainfall in the catchments
·
Collection and evaluation of data and frequencies
of heavy rain fall
·
Mean monthly temperature,
Hydrological Studies:
Gauge and discharge
observation, past flood, hydrographs to fix spillway capacity, rain fall runoff
correlation studies etc.
·
Loss of storage capacity by silting is a vary vital issue for
determining the useful life of the reservoir.
·
Sediment observation shall be carried for 3 years for suspended
load, bed load and natural soil conditions including catchment characteristics from point of
erosion.
Ground water investigations and permeability testing are necessary for
several reasons. These investigations provide the basis for design of any dewatering
systems required during construction. They also provide the data to evaluate
the reservoir’s capability to impound water and to design seepage and uplift
control required in the foundation beneath the dam and in the abutments. These
data also provide the basis for making assumptions of uplift on rock wedges.
Feel free to write